Environmental Screening and Preliminary Assessment Report

Dr. Harish Kumar Gupta

3. PROJECT ALIGNMENT DESCRIPTION

The Projected Corridor STARTS from Chainage @ 00.000 Km (NH – 74) with coordinates (28°57’19.26” N and 79°25’47.66” E) and traverses through mostly government land and paddy fields and circles the City. Rudrapur Bypass Road Crosses NH – 87 (New NH – 09) and NH – 74 (New NH – 309) and the road ENDS @ Chainage 20.655 Km (NH – 87) with coordinates (29°0’54.61” N and 79°24’2.03” E). The total length of the alignment is 20.655 Km.